Division of Surface Water Permit to Install Application Status
Report Creation Date: 4/24/2018 6:00:03 AM
   
County
Applicant
Project Name
Contact
PTI No
Status
Allen
     
 
Allen County Sanitary Engineering
e-one Pumps and Force Main In Cable Road
Christie, Margaret
1216597
Approval - 03/27/2018
 
Allen County Sanitary Engineering
e-one Pumps and Froce Main In Yoder Road
Christie, Margaret
1216594
Approval - 03/27/2018
 
Lima Refining Company
Lima Refining - Substation 16D3 Power Equipment Center
Christie, Margaret
1176157
Revision Requested - 10/31/2017
Ashtabula
     
 
ARU Campgound and Marina
ARU Campground and Marina Watstewater Collection System Improvements
Rivera, Destinie
1176361
Under Review
 
Ashtabula County Dept.of Environmental
Lake Road West Sanitary Sewer
Bayer, Zachary
1217668
Under Review
 
Bargin Bin Store LLC
The Bargain Bin Store LLC
Cycyk, Allison
1212787
Approval - 04/10/2018
 
CITY OF GENEVA
Wastewater Treatment Facility Improvements
Lin, Wen-Tong
1218966
Under Review
 
Cynthia Nye Marsh Hartsgrove Twp. Park
Cynthia Nye Marsh-Hartsgrove Twp. Restroom Facility
Simpson, Ronald
1198179
Under Review
 
Elkem Metals Company - Ashtabula LP
EMC Ashtabule Inc. PTI closure plan, wastewater settling ponds 1A, 2, 4D, and 5C
Cycyk, Allison
1213355
Revision Requested - 02/23/2018
 
EMC Ashtabula Inc.
EMC Ashtabula ponds 3 & 3A leachate pumping and treatment
Wilson, Virginia
1103171
Revision Requested - 09/22/2016
 
Great Lakes Medieval Faire
Wastewater Treatment System Improvements - Great Lakes Medieval Faire
Cycyk, Allison
1214508
Approval - 04/10/2018
 
Gwen's Catering
Gwen's Catering
Cycyk, Allison
1212079
Revision Requested - 03/09/2018
 
Pure Joy Spa
Pure Joy Spa Wastewater Upgrades
Cycyk, Allison
1209672
Revision Requested - 02/20/2018
 
Running Horse Farm
Running Horse Farm Banquet Center
Cycyk, Allison
1221454
Revision Requested - 04/11/2018
 
Village of Orwell
Village of Orwell WWTP - Headworks Improvements
Cycyk, Allison
1221722
Revision Requested - 04/19/2018
 
Willow Lake Campground
Improvements for Willow Lake Campgrounds - Phase 2
Rivera, Destinie
1209353
Approval - 04/03/2018
Athens
     
 
Elsea Inc
HAPPY VALLEY MHP FLOW EQUALIZATION ADDITIONAL STORAGE
Mcginnis, Kurt
1220406
Under Review
 
Montle LLC
The Port Campground and Docks Sewerage System Improvements
Mcginnis, Kurt
1213178
Under Review
 
Ron Campbell
Ron Campbell Apartments Sewage Treatment System Improvements
Mcginnis, Kurt
1209047
Under Review
Auglaize
     
 
The Dannon Company Inc (IDP)
The Dannon Company WWTP Calamity Tank Improvements
Ko, Jason
1219580
Approval - 04/17/2018
 
Village of Minster
Minster - Fifth St Condos Sanitary Extension
Ko, Jason
1219339
Approval - 04/06/2018
 
Village of Minster
Sanitary Sewers, Pump Station & Force Main For South Industrial Park
Ko, Jason
1219248
Approval - 04/06/2018
Belmont
     
 
Barnesville STP
Backwash line
Pennington, Aaron
1153676
Revision Requested - 06/26/2017
 
Eastern Ohio Regional Wastewater Auth
Long Term Control Plan
Stevenson, Abbot
659884
Under Review
 
ODNR-Division of Parks & Recreation
Barkcamp State Park, Campground Upgrades
Pennington, Aaron
1207067
Approval - 04/09/2018
Butler
     
 
Butler County Board of Commissioners
Shannon Ridge
Ware, Ronald
1218382
Approval - 03/27/2018
 
Butler County Board of County Commissioners
TID Development
Ware, Ronald
1222338
Under Review
 
City of Oxford
Gaslight Avenue at Stewart Square
Ware, Ronald
1218390
Approval - 03/27/2018
 
City of Trenton
Maple View, Section 4
Ware, Ronald
1220178
Approval - 04/09/2018
 
Stephen Michael Mortenson Jr.
Post and Frame Barn
Ware, Ronald
1219799
Approval - 04/06/2018
 
TIE Investments
Green Acres Landscaping and Nursery
Ware, Ronald
1217026
Approval - 04/06/2018
 
Valicor Environmental Services
Valicor Environmental Services - Wastewater Pretreatment System
Harvey, Sarah
1200331
Approval - 04/16/2018
Carroll
     
 
Rosebud Mining Co
Rosebud Carrollton Mine
Foster, Scott
948447
Revision Requested - 03/22/2016
Champaign
     
 
Madriver Farm Market
On Site Wastewater Plan for the Madriver Farm Market
Vonderembse, Glen
1159108
Under Review
Clark
     
 
Clark County Department of Utilities
Clark County Southwest Regional Sludge Storage Building
Ostendorf, Robert
1218732
Approval - 03/27/2018
 
Sure Fire Investments FLP
Stafford Road Sanitary Sewer Extension
Ostendorf, Robert
1220167
Revision Requested - 04/18/2018
Clermont
     
 
Clermont County Bldg Water Resources Dept
Pine Bluffs Subdivision Section 3
Leibfritz, Sandra
1222660
Revision Requested - 04/23/2018
 
Clermont County Water Resources Department
Kline Station Subdivision Section 1
Leibfritz, Sandra
1221424
Under Review
 
Eric Black
EB Automotive Holding Tank
Leibfritz, Sandra
1221660
Under Review
Clinton
     
 
Alkermes Inc
Alkermes - Bulk Line 6 Expansion
Harvey, Sarah
1217491
Under Review
 
Matthew 25 Ministries
Kirkwood Waste Water Treatment Plant Upgrades
Sarle, Edward
1220928
Under Review
 
ODNR - Division of Parks & Watercraft
Cowan Lake State Park WWTP Improvements
Sarle, Edward
1215457
Approval - 04/11/2018
 
Ohio Department of Natural Resources
Cowan Lake State Park Beach Wastewater Improvements
Sarle, Edward
1217884
Revision Requested - 03/15/2018
 
RLR Investments LLC
RLR - Roberts Development New Pump Station
Leibfritz, Sandra
1222089
Under Review
Columbiana
     
 
City of Columbiana
Metz Road SSX
Bayer, Zachary
1217670
Approval - 04/03/2018
 
New Day Recovery LLC
New Day Recovery Middleton Addiction Recovery Facility
Sunkle, Melinda
1219166
Under Review
Coshocton
     
 
ALDI, INC
Aldi #55 Coshocton
Poling, Emily
1221312
Under Review
Crawford
     
 
Colonel Crawford Local School District
Colonel Crawford School - Magnesium Hydroxide Feed System
Ko, Jason
1222240
Under Review
 
SUNSET SPRINGS CAMPGROUNDS
Sunset Springs Camground new grinder pump pressure sewers (Lines A,D,F,G,H,I)
Ko, Jason
1222809
Under Review
 
SUNSET SPRINGS CAMPGROUNDS
Suset Springs Campground New Grinder Pump Pressure Sewer (Lines B, C and E)
Ko, Jason
1222806
Under Review
Cuyahoga
     
 
Arconic Inc
Wastewater Pretreatment System Improvements
Kniss, Donna
1221457
Under Review
 
BD Euclid Ave LLC
Euclid Midtown Townhomes
King, Suzanne
1157123
Revision Requested - 04/05/2018
 
Chagrin Highlands Inc
Orange Place Subdivision - Phase 1 Chagrin Highlands
Rivera, Destinie
1214143
Revision Requested - 03/08/2018
 
Charter Steel
Charter Steel Rolling Mills Water Treatment Plant: Modifications to PTI 557560
Kniss, Donna
1215296
Approval - 04/12/2018
 
City of Lakewood
Lakewood - High Rate Treatment Facility WWTP Imp
Mbah, Valentine
1217389
Under Review
 
City Plating and Polishing LLC
City Plating - Pretreatment System Upgrade
Kniss, Donna
1218953
Under Review
 
Cleveland Metroparks
Brecksville Nature Center
Whittingham, Ian
1109830
Approval - 04/03/2018
 
Columbia Park MHC East LLC
Columbia Park MHC East LLC – WWTP Improvements
Workman, Brianne
1218956
Revision Requested - 03/15/2018
 
Coral Westhampton LLC
Westhampton - Phase 2C
Bayer, Zachary
1213653
Under Review
 
Cuyahoga County Dept. Public Works
Reconstruction and widening of Royalton Rd to 3 lanes in the City of N. Royalton
Rivera, Destinie
1213304
Revision Requested - 04/09/2018
 
CUYAHOGA VALLEY NATIONAL PARK
Cuyahoga Valley National Park, Breackville, Ohio - Repalce or Renovate Sewage Lift Station
Rivera, Destinie
1209892
Approval - 04/03/2018
 
Edward's Financial Group
The Estates 8 Subdivision
Bayer, Zachary
1217301
Under Review
 
Galilee Property LLC
Center Ridge Townhomes
Bayer, Zachary
1211583
Under Review
 
Garland New Homes Inc
The Hilliard Court Subdivision
Bayer, Zachary
1217679
Revision Requested - 03/14/2018
 
James Doyle
South Riverdale Lot Split and Assembly Plat Site Development Plan
Rivera, Destinie
1208882
Revision Requested - 12/18/2017
 
K Hovnanian Homes
Schady Reserve Subdivision No.4
Bayer, Zachary
1218105
Under Review
 
Northeast Ohio Regional Sewer District
London Road Relief Sewers
Mbah, Valentine
1220400
Under Review
 
Northeast Ohio Regional Sewer District
NEORSD – Doan Valley Relief and Consolidation sewer
Mbah, Valentine
1216488
Under Review
 
Olmsted Falls Board Of Education
Early Chioldhood Learning Center WWTP Upgrades
Workman, Brianne
1220093
Revision Requested - 04/13/2018
 
Perry Homes
Chestnut Woods - Section 3 Subdivision - Phase 5
Rivera, Destinie
1209890
Under Review
 
Petros Homes
The Village Phase 2
Bayer, Zachary
1220090
Under Review
 
South Brecksville Development Co
The Preserve at Parkside
Rivera, Destinie
1209080
Under Review
 
St. Luke The Evangelist Orthodox Church
St. Luke The Evangelist Orthodox Church
Workman, Brianne
1219724
Revision Requested - 04/03/2018
 
Starwood Retail Partners
Great Northern Restaurant Building
Simpson, Ronald
1168986
Under Review
Defiance
     
 
WILLOW CREEK MARKET
Wastewater Treatment Facilities For Willow Creek Market
Gall, Andrew
1219037
Approval - 04/09/2018
Delaware
     
 
Buckeye Valley School District
Buckeye Valley West Elementary School WWTP Project
Owen, John
1200315
Under Review
 
Delaware Development, LTD
Coughlin's Crossing, Phase 1
Owen, John
1218305
Under Review
 
Highbanks Metro Park
Installation of 2 Pre-cast Restrooms with 2,000 Gallon Capacity Vaults Each
Zhang, Julia
1219646
Under Review
 
Jerry McClain Companies
Sunbury Estates
Owen, John
1222418
Under Review
 
M/I Homes
Scioto Ridge Crossing - Section 3
Owen, John
1222105
Under Review
 
M/I Homes of Central Ohio, LLC
The Pines, Section 1, Phase A & B
Owen, John
1222537
Under Review
 
Pulte Homes of Ohio LLC
Shelly's Retreat at Carpenter's Mill
Zhang, Julia
1215806
Approval - 04/11/2018
 
Pulte Homes of Ohio, LLC
Heatherton Section 7/8
Owen, John
1220541
Under Review
 
Pulte Homes of Ohio, LLC
Shelly's Retreat at Carpenter's Mill Pump Station Improvements
Zhang, Julia
1219477
Under Review
 
Pulte Homes of Ohio, LLC
The Communities at Glenross Section 15
Owen, John
1222391
Under Review
Erie
     
 
Capital Growth Buchalter
Sanitary Sewer Extension, Grinder Pump Station and Force Main For Huron Dollar General
Williams, Justin
1215656
Approval - 04/06/2018
 
HURON DEVELOPMENT PARTNERS, LLC
Sanitary Sewers For The Courtyards at Plum Brook Phase 1
Williams, Justin
1218534
Approval - 04/03/2018
 
MHD Corporation
MHD Bayshore Campbround 2018 RV Expansion
Williams, Justin
1215652
Revision Requested - 03/01/2018
 
MILAN RD PROPERTIES
Quarry Crossing Frontage Road extension lot 5 plat 13
Celesti, Nina
1207106
Revision Requested - 12/04/2017
Fairfield
     
 
C.J. Kraft Enterprises, Inc.
Bay Packing Animal Waste Holding Pond
Owen, John
1198141
Under Review
 
Hickman Properties I
Misty Meadows Section 3, Phase 2
Cleveland, Daniel
1218543
Approval - 03/27/2018
 
Lancaster Camp/Church Assembly Assoc
Lancaster Camp Ground Sanitary Sewer Extension
Owen, John
1220191
Revision Requested - 04/13/2018
 
Redwood Acquisition
Greengate Blvd Sewer Extension
Owen, John
1220872
Under Review
Fayette
     
 
Crop Production Services
Crop Production Services
Sapp, Michael
1212970
Under Review
 
Fayette County Commissioners
Culpepper Area Sewer Improvements
Sapp, Michael
1220721
Under Review
Franklin
     
 
Belmont House LLC
Belmont House
Zhang, Julia
1222413
Under Review
 
Blacklick Woods Metro Park
Installation of 1 Pre-cast Restroom with 2,000 gallon capacity vault
Zhang, Julia
1219692
Revision Requested - 04/13/2018
 
Capital Health Services
Scioto Community
Zhang, Julia
1221437
Revision Requested - 04/19/2018
 
Central Ohio BioEnergy LLC
Central Ohio BioEnergy, LLC NRRS
Matz, Suzanne
1008264
Under Review
 
City of Columbus, Sewerage & Drainage
Columbus - Woodward Avenue Sanitary Sewer Imp
Laake, Ryan
1212058
Under Review
 
City of Columbus, Sewerage & Drainage
Southerly WWTP Digestion Process Expansion (S90)
Dragovich, Joseph
1209421
Under Review
 
Columbus City of Sewer and Drain
Columbus - Jackson Pike Biosolids Land Application Imp
Dragovich, Joseph
1146066
Under Review
 
Columbus Parks and Recreation Department
Sanitary Sewer Relocation for Indian Mound Community Center, 3901 Parsons Avenue, Columbus, OH
Zhang, Julia
1221159
Under Review
 
Crescent at Central Park LLC
Crescent at Central Park
Cleveland, Daniel
1217305
Under Review
 
Fairway Realty
Henderson Road Residences
Zhang, Julia
1222226
Under Review
 
Franklin County Sanitary Engineer
Village of Harrisburg Sewer Extension (Chenoweth Street)
Owen, John
1222184
Under Review
 
JAZ Real Estate Holdings, LLC
Germain Infiniti Service Center & Car Wash Sanitary Improvements
Zhang, Julia
1219555
Under Review
 
M/I Homes of Central Ohio, LLC
Minerva Park Phase 5, 6 & 7
Zhang, Julia
1218568
Approval - 04/11/2018
 
Nationwide Realty Investors
Grandview Yard L Block
Zhang, Julia
1222109
Under Review
 
Prospect Wango, LTd
University City (Columbus Project Number CC-17975)
Owen, John
1219577
Approval - 04/10/2018
 
Pulte Homes of Ohio, LLC
Crossings at Rocky Fork Section 1
Zhang, Julia
1222963
Under Review
 
United Dairy Farmers Inc
UDF - Reynoldsburg, OH
Zhang, Julia
1200285
Under Review
 
Worthington Garden Apartments
Worthington Garden Apartments - Wastewater Improvements
Matz, Suzanne
610508
Under Review
 
Worthington Industries Inc
Worthington Industries Sanitary Sewer Extention - Park Restroom
Owen, John
1219528
Under Review
Fulton
     
 
Swanton, Village of
Swanton - Project 7 Church, Harrison, Lawrence Sewer Separation
Aljamal, Samih
1208645
Under Review
 
W B Ranch
WB Ranch
Gierhart, Ryan
869133
Under Review
Gallia
     
 
Gallipolis, City of
First Avenue and Spruce Street Sewer Extension
Neil, Kerry
1166007
Revision Requested - 09/18/2017
Geauga
     
 
Adele Sohm
13859 Main Market Road Wastewater Improvements
Kinney, Marlene
1218109
Under Review
 
Barn Star Properties Ltd.
OSSO Wastewater System
Kinney, Marlene
1200183
Approval - 04/17/2018
 
Geauga City Dept of Water Resources
Auburn Corners WWTP Expansion & Troy Oaks Pump Station
Kinney, Marlene
1219731
Under Review
 
Geauga County Dept of Water Resources
Bershire Industrial Park WWTP UV Replacement
Kinney, Marlene
1222119
Under Review
 
Geauga Park District
Geauga Park District - Ellerin Property Improvements
Bayer, Zachary
1217998
Revision Requested - 04/05/2018
 
Heritage Hill Stables LLC
Heritige Hill Stables LLC - OSTS Improvements
Kinney, Marlene
1221990
Under Review
 
Marsh Valley
Marsh Valley Forest Products
Rivera, Destinie
1208349
Approval - 04/11/2018
 
VILLAGE OF BURTON
Wastewater Treatment Plant Refurbishment
Mbah, Valentine
1026985
Under Review
Greene
     
 
Greene County Engineering Department
Claiborne Greens at Stonehill Village Phase 4
Sarle, Edward
1219484
Approval - 04/10/2018
 
Renergy Inc
Dovetail Bioenergy Process Reconfiguration Project
Sarle, Edward
1141952
Under Review
Guernsey
     
 
Rosebud Mining Company
Ginger Bend Mine
Foster, Scott
1026845
Revision Requested - 02/26/2015
Hamilton
     
 
BASF Corporation
BASF Corporation Esters Plant Pretreatment System
Harvey, Sarah
1159377
Under Review
 
BWAY Corporation
BWAY Corporation - Sewage Treatment System Replacement
Vonderembse, Glen
1216660
Under Review
 
Fusite Division-Emerson Electric
Fusite - Emerson Electric
Harvey, Sarah
1169576
Revision Requested - 03/27/2018
 
GE Aviation
North Utility Plant - Water Conditioning Process
Osika, Mary
1208993
Approval - 04/05/2018
 
James Shriver
Incremental replacement septic system
Vonderembse, Glen
1222652
Under Review
 
Jeffrey Allen Corporation
Jeffrey Allen Corporation Ultraviolet Disinfection Unit Installation
Vonderembse, Glen
1157598
Under Review
 
Kinder Morgan Operating LP "C"
River Transportation Terminal Salt pad Pavement and Stormwater Collection and Discharge
Harvey, Sarah
1152327
Revision Requested - 11/28/2017
 
MSD of Greater Cincinnati
10240405 Ponderosa Woods Pump Station Elimination SS#6403
Vonderembse, Glen
1209582
Revision Requested - 01/05/2018
 
MSD of Greater Cincinnati
Fort Scott Subdivision Phase 4-Sanitary Sewer No. 6768
Osika, Mary
1219809
Approval - 04/11/2018
 
MSD of Greater Cincinnati
Kemper Mill Village Pump Station upgrade
Vonderembse, Glen
1150217
Withdraw - 04/13/2018
 
MSD of Greater Cincinnati
Neighborhoods at Summit Park SS 6753
Osika, Mary
1220516
Approval - 04/11/2018
 
MSD of Greater Cincinnati
Polk Run Non Potable Water upgrades and UV System / Post Aeration Improvements
Vonderembse, Glen
1197609
Under Review
 
MSD of Greater Cincinnati
Prospect Woods Pump Station Upgrade
Vonderembse, Glen
1151923
Under Review
 
MSD of Greater Cincinnati
Stewart Rd Local Sewer (Hns 5706-5710), PID 10370050 SS#6560
Osika, Mary
1220169
Approval - 04/12/2018
 
MSD of Greater Cincinnati
Taylor Creek Wastewater Plant Disinfection upgrade, project 10221245, Sanitary Sewer 6732
Vonderembse, Glen
1220170
Under Review
 
Nehemiah Manufacturing LLC
Nehemiah South Street Manufacturing Waste Water pH Management System
Harvey, Sarah
1219806
Under Review
Hancock
     
 
Best Construction
Best Liberty Addition
Donnelly, Michael
1222701
Under Review
 
Best Construction
Deer Landing 1st Addition
Donnelly, Michael
1222597
Under Review
 
KOEHLER BROTHERS
Penrose Drive Sanitary Sewer
Donnelly, Michael
1213026
Under Review
Harrison
     
 
Harrison County Water and Sewer District
Faith Ranch Sanitary Sewer Extension
Poling, Emily
1207068
Revision Requested - 01/05/2018
 
Harrison County Water and Sewer District
Harrison County Home Sanitary Sewer
Poling, Emily
1220816
Under Review
 
Mwcd-Tappan Lake Pk.
TAPPAN LAKE PARK - PHASE I CAMPGROUND IMPROVEMENTS
Poling, Emily
1207637
Approval - 04/03/2018
 
Rosebud Mining Co
Stautner Mine
Foster, Scott
1204437
Under Review
Henry
     
 
City of Napoleon
Napoleon - HEN-Industrial Drive
Christie, Margaret
1221571
Under Review
 
City of Napoleon
Napoleon - Williams Pumping Station Replacement
Dragovich, Joseph
1213415
Under Review
 
Village of Holgate
Holgate - Pump Station Replacement
Aljamal, Samih
1153278
Revision Requested - 05/23/2017
Highland
     
 
LT Land Development LLC
Lakeview Estates
Ware, Ronald
1220952
Revision Requested - 04/04/2018
Holmes
     
 
B&P Campground
Arrow Point Campground
Stoll, Dean
701516
Under Review
 
Holmes Cheese Company
Holmes Cheese Total Dissolved Solids Flow Augmentation System
Wilson, Victoria
1144125
Under Review
 
Travel Report of America
Wally World Campground
Rivera, Destinie
1216758
Revision Requested - 03/12/2018
Huron
     
 
CSX Transportation Inc
CSX Willard Yard Transportation Inc. Wastewater Treatment Facility
Martin-Hayden, Dana
1149834
Revision Requested - 09/15/2017
 
Mark Chase
New London - Industrial Drive Roadway Extension
Martin-Hayden, Dana
1219254
Revision Requested - 04/13/2018
 
Village of Greenwich
Greenwich - Seminary Street roadway and sewer imporvements Phase 1
Martin-Hayden, Dana
1214735
Approval - 04/12/2018
 
Village of Wakeman
Rt 20/Rt60 Sanitary Pump Station improvements
Martin-Hayden, Dana
1218983
Revision Requested - 04/13/2018
Jackson
     
 
Tom O'Brien - Shelly & Sands, Inc.
ODOT Project 1099 (2009), Jackson County - S.R. 32- 2.78
Bernstein, Jonathan
766821
Under Review
Jefferson
     
 
Jefferson County Board of Commissioners
Jefferson County - Amsterdam Area Sewer & WWTP
DeNiro, Dennis
1214128
Under Review
Lake
     
 
City of Eastlake
Waverly 1 Relief / Replacement Sewer
Mbah, Valentine
1208326
Approval - 04/10/2018
 
Eye-Will Development
Hillshire Woods Condominiums Phae lll
Bayer, Zachary
1220069
Approval - 04/12/2018
 
Lake Co Metroparks
Lake County Metroparks - Blair Rd. Shelter
Dejanovic, Zorica
1222044
Under Review
 
Lake County UtilitIies Department (LCUD)
St. James Relief Sewer
Bayer, Zachary
1219729
Under Review
 
Lake Metroparks
Lake Metroparks Penitentiary Glen Nature Play Restroom
Bayer, Zachary
1215848
Approval - 04/12/2018
 
Mapleview Village LLC
Riverwood Village Sudbivision No.1
Bayer, Zachary
1212077
Under Review
 
Meijer, Inc.
Meijer #309- Mentor, Ohio
Rivera, Destinie
1219264
Revision Requested - 03/29/2018
 
On the Green Development, LLC
Fairway Glenn Subdivision, Phae ll
Rivera, Destinie
1219271
Under Review
 
Riverside Board of Education
Concord-Hambden Road Elementary School
Bennage, Jennifer
1214148
Under Review
Lawrence
     
 
HarbisonWalker International, Inc.
Harbison Walker South Point
Knapp, Jack
1217652
Approval - 04/11/2018
Licking
     
 
CITY OF NEWARK OHIO
Newark Downtown Renovation - Phase I, Proposal Request 23
Owen, John
1221726
Under Review
 
Southwest Licking Community Water
Water Treatment Center - R.O. Concentrate Discharge Force Main
Owen, John
1219604
Under Review
 
Summit Ridge Estates
Summit Ridge Estates Phases 3 & 4
Owen, John
1219168
Under Review
 
Village of Hanover
2017 Village of Hanover Post Aeration WWTP Project
Owen, John
1217362
Under Review
Logan
     
 
Jason D Kremer
Flip Flop Cove Campgrounds
Ware, Maureen
1211306
Revision Requested - 01/18/2018
Lorain
     
 
Amherst Exempted Village Schools
Powers Elementary School
Bayer, Zachary
1215953
Under Review
 
Avon Lake, City of
Curtis Drive Sanitary Sewer Rehabilitation Project
Moody, Christopher
1222118
Under Review
 
Cambrad Development LLC
The Reserve at Beaver Creek Subdivision
Rivera, Destinie
1213948
Approval - 04/12/2018
 
City of North Ridgeville
Luanne Drive Pump Station Replacement
Bayer, Zachary
1212354
Approval - 04/05/2018
 
Grafton Village of
Grafton - Oak Street Improvements
Lin, Wen-Tong
1200353
Under Review
 
Jailhouse Tavern Tromier Posterity Trust
The Jailhouse Tavern Wastewater Treatment System Upgrade
Dejanovic, Zorica
1217996
Under Review
 
K Hovnanian Homes
Meadow Lake Phase 15 Sanitary Modification
Bayer, Zachary
1220429
Under Review
 
K Hovnanian Homes
Waterbury - Phase 9
Bayer, Zachary
1213669
Approval - 04/03/2018
 
Pirhl Developers, LLC
The Cottages at Riverview
Rivera, Destinie
1219719
Under Review
 
The Meritage Group L.P.
The Reserve at Winfield Farm - Phase 2
Simpson, Ronald
1197497
Under Review
 
The Meritage Group L.P.
The Reserve at Winfield Farm - Phase 3
Bayer, Zachary
1219255
Revision Requested - 03/30/2018
 
United Model Homes LLC
Chandon Subdivision No. 3
Bayer, Zachary
1221062
Under Review
 
Village of Sheffield
Sheffield Village Municipal Bld Trash Trap
Dejanovic, Zorica
1217307
Approval - 04/06/2018
Lucas
     
 
ANTHONY WAYNE LOCAL SCHOOLS DISTRICT
Anthony Wayne Schools Operations Bulding
Donnelly, Michael
1219737
Under Review
 
DLR Acquisitions
Sanitary Sewer Extension For The Preserve Plat Two
Donnelly, Michael
1220196
Approval - 04/12/2018
 
GS ENGINEERING
GS Engineering New Warehouse
Donnelly, Michael
1221767
Under Review
 
STONEY CREEK PARTNERS, LLC
Stoney Creek Plat 1
Donnelly, Michael
1222702
Under Review
Madison
     
 
Kroger Co
Kroger Fresh Eats #700 of West Jefferson Public Water and Sewer Improvements
Owen, John
1164080
Under Review
 
Madison Plains Schools
Wastewater Disinfection System
Zhang, Julia
1219164
Under Review
Mahoning
     
 
A&K Gentile Properties
Lake Hamilton Estates
Bayer, Zachary
1213306
Revision Requested - 02/16/2018
 
City of Youngstown WWTP
Youngstown WWTP primary effluent pump station and appurtenances improvements
Laake, Ryan
1213358
Under Review
 
Heidi Garwig
Garwig Sewer Extension
Bayer, Zachary
1211400
Approval - 04/03/2018
 
Patriot Water Treatment LLC
Patriot Water Treatment Youngstown Phase I
Kniss, Donna
1217306
Under Review
 
Sanitary Engineering Dept of Mahoning Co
Five Points Pump Station
Bayer, Zachary
1219727
Revision Requested - 03/30/2018
Marion
     
 
Capital Growth Buchalter
Proposed Dollar General
Cohen, Mary
1221166
Under Review
Medina
     
 
Friendly Inn
Friendly Inn
Dejanovic, Zorica
1220724
Revision Requested - 04/10/2018
 
Gombar Winery
Gombar Winery
Trocchio, Joseph
1155514
Revision Requested - 06/16/2017
 
Medina County Sanitary Engineers
Liverpool Wastewater Treatment Facility
Workman, Brianne
1149484
Under Review
 
Pulte Homes of Ohio, LLC
Blooming Acres Phase 3
Bayer, Zachary
1217304
Revision Requested - 03/14/2018
 
Pulte Homes of Ohio, LLC
Forest Creek Phase 4
Bayer, Zachary
1211712
Revision Requested - 02/02/2018
 
Shannondoah, LLC
Autumn Meadows Subdivision, Phase 4
Bayer, Zachary
1221024
Revision Requested - 04/09/2018
 
Shannondoah, LLC
Quail Ridge
Simpson, Ronald
1207844
Under Review
 
Speedway / EMRO Marketing Co
Rebuild existing Speedway Store #3650; 4600 sq. ft. building for fueling station
Workman, Brianne
1221724
Revision Requested - 04/19/2018
 
The Restored Church of God
The Restored Church of God Subdivision
Bayer, Zachary
1221453
Under Review
 
Westfield Lakes LLC
Westfield Terrace Phase Two and Phase Three
Shriver, Laura
1222447
Under Review
 
White Birch Barn LLC
White Birch Barn Onsite Treatment System
Workman, Brianne
1167451
Revision Requested - 09/26/2017
Meigs
     
 
Agri-Leasing LLC
Meigs County Medical Marijuana facilty
Foster, Scott
1218701
Approval - 04/11/2018
Mercer
     
 
Cooper Farms Processing
Cooper Farms-St Henry Plant Pretreatment Improvements
Martin-Hayden, Dana
1213745
Approval - 04/17/2018
 
Pax Machine Works Inc
Pax machine Works Inc centrifuge
Martin-Hayden, Dana
1212215
Approval - 04/09/2018
Miami
     
 
City of Huber Heights
Carriage Trails Section 8, Phase 1
Holmes, Geoffrey
1220695
Approval - 04/12/2018
 
Hampton Woods Inc
Stonebridge Meadows Section 6
Holmes, Geoffrey
1220518
Approval - 04/10/2018
 
Hampton Woods Inc
Stonebridge Meadows Section 7
Holmes, Geoffrey
1220521
Approval - 04/10/2018
 
Indian Ridge Properties
Indian Ridge Section 7
Holmes, Geoffrey
1220527
Approval - 04/17/2018
Montgomery
     
 
Charles V Simms Development
Savannah Place at Yankee Trace
Reynolds, Joseph
1219800
Approval - 04/10/2018
 
City of Dayton-Dayton Int'l Airport
Northwest Development Area - Water and Sewer Improvements
Reynolds, Joseph
1220526
Under Review
 
City of Huber Heights
Artisan Walk Section Two
Reynolds, Joseph
1220172
Approval - 04/10/2018
 
City of Huber Heights
Cosner Drive Lift Station Replacement
Reynolds, Joseph
1220524
Under Review
 
City of Miamisburg
Staco Proposed Office/Industrial Bldg
Reynolds, Joseph
1219816
Approval - 04/10/2018
 
City of Union
Union WWTP Phase 1 Improvements
Reynolds, Joseph
1222337
Under Review
 
Trails Partners LLC
Trails of Saddle Creek, Section 9
Reynolds, Joseph
1220999
Approval - 04/17/2018
 
VWC Holdings Ltd
The Villages of Winding Creek, Creekside at Winding Creek, Section 4
Reynolds, Joseph
1222645
Under Review
Morgan
     
 
Dwight Burt
STOCKPORT RV PARK
Poling, Emily
1215344
Under Review
Morrow
     
 
W Partners
Lakeview Estates Mobile Home Park
Zhang, Julia
1221191
Under Review
Multiple counties
     
 
JJ Precision Machine Inc
Statewide Sewage Biosolids Pasteurization Process
Yakhnitskiy, Aleksandr
1103248
Revision Requested - 02/08/2017
Muskingum
     
 
Dunfalls Association, Inc.
Dunfalls Association Inc. Sewage Treatment Plant UV disinfection system
Tschudy, Dustin
1216698
Approval - 04/18/2018
 
Englefield Oil Company
Zanesville Bulk Oil Facility
Snell, Frederick
425610
Under Review
 
Grow Ohio Pharmaceuticals
FACILITY WASTEWATER COLLECTION AND DISPOSAL
Walton, Christopher
1222748
Under Review
 
Meadow Farm Church
WASTEWATER TREATMENT SYSTEM
Walton, Christopher
1153830
Under Review
 
Muskingum County Commissioners
Muskingum County Sewer District/Pembroke Avenue Force Main
Walton, Christopher
1220783
Approval - 04/18/2018
Noble
     
 
Noble County Commissioners
Belle Valley Sanitary Sewer Relocation
Hammer, Nicholas
1218703
Approval - 04/18/2018
Ottawa
     
 
GBT Realty
Dollar General Store
Williams, Justin
1220367
Under Review
 
LUCKEY FARMERS, INC.
Septic system and holding tank plans for Luckey Farmers
Williams, Justin
1222771
Under Review
 
MATT HOLCOMB
Wastewater Treatment Facilities For Matt Holcomb
Williams, Justin
1219743
Under Review
 
Paradise Acres Campground
Sanitary Sewers For Paradise Acres RV Park Expansion
Williams, Justin
1219734
Approval - 04/12/2018
Paulding
     
 
Haviland Energy LLC
Haviland Energy Remote Pond
Gall, Andrew
1154429
Revision Requested - 08/22/2017
 
Village of Paulding
Phase 3 Combined Sewer Separation
Dragovich, Joseph
1208412
Under Review
Perry
     
 
Perry County Industrial Development Co LTD
City Gate Residential
Messerly, Daniel
449038
Revision Requested - 08/18/2004
Pickaway
     
 
Earnhart Hill Regional Water & Sewer District
Earnhart Hill Regional Water & Sewer District River Drive WWTP Improvements
Owen, John
1168216
Approval - 03/28/2018
 
Shawnee Grove Housing Partners, LLC
Shawnee Grove Apartments
Zhang, Julia
1222094
Under Review
Pike
     
 
Waverly, City of
ST. RT. 335 sanitary sewer extension
Knapp, Jack
1221133
Under Review
Portage
     
 
Allen Aircraft Products Inc Metal Finish
Allen Aircraft Wastewater Treatment System Replacement
Kniss, Donna
1214156
Approval - 04/05/2018
 
B. Montgomery Deerfield Methodist Church
B. Montgomery Deerfield Methodist Church Replacement wastewater treatment system for an existing fai
Barbis, Melanie
1155842
Revision Requested - 03/08/2018
 
Brimfield Township Trustees
Brimfield Township Parks Sanitary Pump Station - Community Center
Bayer, Zachary
1217994
Under Review
 
Lemmon & Lemmon Inc
Maplecrest Development
Bayer, Zachary
1218310
Revision Requested - 03/22/2018
 
Neighborhood Development Services
THe Wilds at Harvest Rose
Bayer, Zachary
1211711
Under Review
 
OLIO Development
Raising Cane's Chicken Fingers
Bayer, Zachary
1219268
Approval - 04/09/2018
 
Portage Co Water Resources
Countryside Estates Wastewater Treatment Plant Tank Replacement
Barbis, Melanie
1155512
Under Review
 
RAB Oil & Gas LLC
Green Leaf Medical Ohio
Barbis, Melanie
1208594
Under Review
 
Thomas & Betts Corp
Mogadore Road Groundwater Interceptor Trench Pumping System
Kniss, Donna
1110106
Revision Requested - 10/07/2016
Preble
     
 
Lakengren Water Authority
Lakengren Water Authority - WWTP Improvements
Aljamal, Samih
1207275
Revision Requested - 12/11/2017
 
Seed Time Acres
Seed Time Acres - Corn Crib Septic Tank
Ware, Ronald
1220943
Under Review
 
Seed Time Acres
Seed Time Acres - Event Center Septic Tank
Ware, Ronald
1220937
Under Review
Putnam
     
 
Pro-Tec Coating Company
ProTec Coating Company PTI App Wastewater Treatment and Recycle Systems for New Continuous Galvanizi
Abdullah, Naajy
1221552
Under Review
 
Village of Ottawa
Ottawa - WWTP Headworks
Aljamal, Samih
1080771
Under Review
Richland
     
 
Muskingum Watershed Conservancy District
Sanitary Sewers for Pleasant Hill Lake Cabins
Mix, Michelle
1222008
Revision Requested - 04/18/2018
 
Muskingum Watershed Conservancy District
Sanitary Sewers, Pump Stations & Froce Mains, And Wastewater Treatment Facilities For Charles Mill L
Mix, Michelle
1169510
Approval - 04/12/2018
 
Pittsburg Glass Works LLC
Pittsburgh Glass Works - Process wastewater treatment system Improvements
Mix, Michelle
1222410
Under Review
 
THE RICHLAND COUNTY MENTAL HEALTH
Sanitary sewers for New Beginnings Phase II & Wellness Management Center
Mix, Michelle
1220106
Revision Requested - 03/30/2018
 
Village of Bellville
WWTP Improvements
DeNiro, Dennis
1086460
Under Review
 
Village of Butler
Butler - WWTP Improvements
DeNiro, Dennis
1208149
Revision Requested - 03/05/2018
 
West Cook Development
Bridgewater Phase 4
Mix, Michelle
1222789
Under Review
Ross
     
 
Jeffrey E. Francis
Barn Rehabilitation
Neil, Kerry
1165691
Under Review
Scioto
     
 
State of Ohio Dept Rehab and Corectn
SOCF Rehabilation of Sewer and WWTP Rehabilitation
Knapp, Jack
1219159
Under Review
Seneca
     
 
Ramsey Development LLC
Tiffin West End Development
Abdullah, Naajy
1217282
Approval - 04/11/2018
Shelby
     
 
Dan Paulus
Paulus Acres
Ware, Maureen
1220975
Under Review
 
Everyday Technologies
Everyday Technologies Wash Booth Systems
Ostendorf, Robert
1221667
Revision Requested - 04/18/2018
 
Love's Travel Stops & Country Stores Inc
Loves Travel Stops - Sidney Ohio
Ware, Maureen
1217902
Approval - 04/16/2018
Stark
     
 
A.R. Lockhart Development
Kenyon Creek Estates Phase II and III Sanitary Sewer System
Simpson, Ronald
1197875
Revision Requested - 04/06/2018
 
Brewster Cheese Company
Brewster Cheese Inc., WWTP Upgrade - Increased Clarifier Size, Brewster Ohio
Shriver, Laura
1218456
Under Review
 
City of Alliance
Alliance WWTP Class A Biosolids
Moody, Christopher
1168586
Under Review
 
L. J. Yoder Construction
The Woodlands No. 1 & 2
Rivera, Destinie
1215273
Under Review
 
Leroy Yoder
Gentlebrook Village No. 1
Rivera, Destinie
1211588
Revision Requested - 02/02/2018
 
Louisville,City Of
Louisville WPCC Final Clarifier Improvements
Shriver, Laura
1215523
Under Review
 
McKinley Development Co
The Fountains at Edgewood No. 1
Bayer, Zachary
1220722
Under Review
 
McKinley Development Co
The Fountains at Edgewood No. 2
Bayer, Zachary
1220723
Under Review
 
Schalmo Properties Inc
Sandy Ridge Development - Phase 2
Bayer, Zachary
1221988
Under Review
 
UMH Properties, Inc.
Lake Sherman Village
Wilson, Victoria
1157648
Under Review
Summit
     
 
Bath Road Associates, LLC
French Mill Run Phase 2
Arocho, Ynes
1221720
Under Review
 
City of Akron
Akron – Kelly Conveyance (CSO Rack 3)
Lin, Wen-Tong
1216589
Under Review
 
City of Akron
Sevilla Trunk Sewer Reconstruction
Lin, Wen-Tong
1209230
Under Review
 
City Of Akron Ohio
Hampton Ridge Sanitary Sewer
Lin, Wen-Tong
1219233
Under Review
 
City Of Akron Ohio
Uhler Avenue CSO Rack 27 and Rack 29 Imp
Lin, Wen-Tong
1221842
Under Review
 
City of Fairlawn
Hampshire Road SSX
Bayer, Zachary
1218951
Under Review
 
City of Hudson
City of Hudson Salt Storage Facility & Hudson City Schools Bus Maintenance Garage
Rivera, Destinie
1215844
Approval - 04/03/2018
 
City of Norton
Cleveland - Massillon SSX Phase 2 & 3
Rivera, Destinie
1219261
Revision Requested - 04/09/2018
 
CUYAHOGA VALLEY NATIONAL PARK
Cuyahoga Valley National Park Central Visitor's Center
Rivera, Destinie
1209688
Under Review
 
D.B. Development L. L. C.
Canfield Rd Sewer JEDD for Alexanders MHP
Rivera, Destinie
1212352
Approval - 04/10/2018
 
East New Haven LLC
East New Haven Phase One
Rivera, Destinie
1213303
Approval - 04/03/2018
 
Good Vibrations Enterprises
Good Vibrations Enterprises - WWTP
Allen, Charles
1167600
Approval - 03/28/2018
 
Great Trail Counsel, BSA
Camp Manatoc Restrooms
Rivera, Destinie
1212888
Revision Requested - 02/15/2018
 
KNL Homes Inc
Everett Pointe SSX
Bayer, Zachary
1221032
Revision Requested - 04/09/2018
 
Oak Knolls Condominiums
Oak Knolls Homeowners Association_WWTP Improvements
Allen, Charles
1153871
Revision Requested - 06/09/2017
 
Omni SLF Westlake LLC
Stow Assisted Living
Schubert, Brian
1159803
Under Review
 
Patrick D'Andrea
Dickerson Run Subdivision
Rivera, Destinie
1219258
Revision Requested - 03/29/2018
 
Revere Local School District
New Bath Elementary School Pump Station Mod
Rivera, Destinie
1213307
Revision Requested - 04/16/2018
 
S&A Macedonia LLC
The Reserve at North Woods Subdivision - Phase 2
Bennage, Jennifer
1221983
Under Review
 
Spire Development
Arlington Ridge Townhomes
Rivera, Destinie
1220088
Approval - 04/16/2018
 
Stanik Properties LLC
Heron Crest (Phase 4)
Rivera, Destinie
1214908
Under Review
 
Summit County Dept of Sanitary Sewers
Upper Tusc WWTP No. 36 RBC Replacement project
Lin, Wen-Tong
1215297
Under Review
 
Woodland Villa's LLC
Sourek Trail Improvements
Rivera, Destinie
1220426
Revision Requested - 04/09/2018
 
Woodland Villa's LLC
Woodland Villas Subdivision
Bayer, Zachary
1220427
Revision Requested - 04/06/2018
Trumbull
     
 
Chrystal Owens
Chrystal Owens Salon and Barber Shop
Stevens, Michael
1220730
Under Review
 
City of Girard
Girard WWTP peak flow trtmt & equalization imp
Laake, Ryan
1212829
Approval - 03/27/2018
 
Dollar General
Dollar General Store, Mecca Site
Trocchio, Joseph
1209687
Under Review
 
Living Word Sanctuary
Living World Sanctuary
Trocchio, Joseph
1198831
Approval - 04/16/2018
 
Lordstown Construction Recovery LLC
Lordstown Construction Recovery, Sediment Basin Modifications
Ferguson, Chad
1148780
Revision Requested - 06/26/2017
 
Ohio Department of Natural Resources
ODNR – Statewide Campground Renovation FT 17-18 – Mosquito Lake State Park
Bayer, Zachary
1213650
Approval - 04/05/2018
 
Patriot Water Treatment LLC
Patroit Wastewater Pretreatment Facility
Kniss, Donna
1213308
Under Review
 
Trumbull County Sanitary Eng.
Scott Street Phase 2 Sanitary Sewer Improvement
Fickle, Gretchen
998825
Revision Requested - 09/03/2014
Tuscarawas
     
 
Belden Brick Co
Belden Brick Sedimintation Pond for the Beagle Pits, Permit IM-48
Mcginnis, Kurt
1177306
Under Review
 
Bluff Terminal Co
Mound system for on site wastewater treatment
Mcginnis, Kurt
1220405
Under Review
Union
     
 
Pulte Homes of Ohio LLC
Autumn Rose Woods
Zhang, Julia
1213995
Approval - 04/10/2018
 
Schottenstein Real Estate Group
Jerome Grand at Jacquemin Farms
Owen, John
1219687
Under Review
Van Wert
     
 
Ridgeview Hospital
Ridgeview Behavioral Hospital Building Expansion Project
Esposito, Frank
1160455
Revision Requested - 09/20/2017
 
Timberwoods Camping Resort
Timberwoods Camping Resort 2018 Lot Expansion
Martin-Hayden, Dana
1222559
Under Review
Vinton
     
 
Hamden Real Estates, LLC
Hamden Nursing Home Sewage Treatment Dechlorinatin system
Delvalle, Lemuel
1217766
Approval - 04/17/2018
Warren
     
 
Butler County Board of Commissioners
Union Village - Offsite Sanitary Sewer
Sarle, Edward
1214877
Approval - 04/10/2018
 
Butler County Board of Commissioners
Union Village Phase I
Sarle, Edward
1214874
Approval - 04/16/2018
 
Clemens Development Co
Beehive Assisted Living, Springboro
Sarle, Edward
1219007
Approval - 04/11/2018
 
Harris Mason Processing LLC
Harris Mason Processing Pretreatment System
Harvey, Sarah
1160246
Under Review
 
Municipality of Carlisle
Timber Ridge Section 9
Sarle, Edward
1221427
Approval - 04/18/2018
 
Village of South Lebanon
Public Sanitary Sewer extension for Alexandr Peredrey
Sarle, Edward
1220523
Approval - 04/12/2018
 
Village of South Lebanon
Wynstead Subdivision Public Sanitary Sewer Extension
Sarle, Edward
1215464
Approval - 03/27/2018
 
Warren County Board of Commissioners
Providence Section 8 Blocks A & B
Sarle, Edward
1221262
Approval - 04/17/2018
 
Warren County Board of Commissioners
Wilson Farms Section Five
Sarle, Edward
1222167
Under Review
Washington
     
 
KRATON Polymers US LLC
KRATON POLYMERS SOUTH SIDE INFRASTRUCTURE IMPROVEMENTS
Pennington, Aaron
1221701
Under Review
Wayne
     
 
Burkey Excavating Inc
Burkey Excavating Inc.
Bayer, Zachary
1216312
Revision Requested - 04/05/2018
 
City of Wooster
Brookside Dr and Oakley Rd Improvements Project
Rivera, Destinie
1220068
Under Review
 
Horst Welding & Fabricating
Horst Welding & Fabrication
Rivera, Destinie
1220726
Under Review
 
Pleasant Home Farm LLC
Wiles Storage Pond
Moody, Christopher
1211412
Revision Requested - 03/26/2018
 
Village of West Salem
West Salem WWTP Improvements
Allen, Charles
1162195
Under Review
 
William Boyd
Winkler Tire Holding Tank
Rivera, Destinie
1215293
Approval - 04/03/2018
Williams
     
 
LOVE'S TRAVEL STOP
Loves Travel Stop SR 49 & Interstate 80 Turnpike, Edon, OH
Donnelly, Michael
1207132
Revision Requested - 04/23/2018
 
LOVE'S TRAVEL STOP
Pump Station & Force Main For Loves Travel Stop
Donnelly, Michael
1207110
Under Review
 
Matsu Ohio Inc
Matsu Ohio Evaporator Replacement
Donnelly, Michael
1213667
Under Review
 
RASSINI CHASSIS SYSTEMS LLC
Rassini Chassis Systems - Wastewater pretreatment metal hydroxide precipitation system
Donnelly, Michael
1208339
Revision Requested - 01/03/2018
Wood
     
 
City of Bowling Green
BG - Donbar and Rosalind Combination Sewer
Christie, Margaret
1222107
Under Review
 
First Solar Inc
Industrial Wastewater Treatment Improvements for First Solar
Mix, Michelle
1221592
Approval - 04/17/2018
 
MEADOWS OF PERRYSBURG, LLC
Sanitary Sewers for Meadows of Perrysburg Manufactured Home Park
Christie, Margaret
1220116
Approval - 04/12/2018
 
Ports Petroleum Company, Inc.
Wastewater treatment facilities for Fuel Mart #767
Mix, Michelle
1221765
Under Review
Wyandot
     
 
CITY OF UPPER SANDUSKY
Upper Sandusky - Ohio WRF Improvements
Aljamal, Samih
1214239
Under Review
 
KASAI NORTH AMERICA
Kasai North America - Urethane Foam Nozzle Washing Process
Cohen, Mary
1207103
Revision Requested - 12/19/2017
 
Vaughn Ind
Sheriden Subdivision
Gall, Andrew
1220113
Under Review